Question: Which risk analysis tool is most commonly used to determine the probability of a project completing on schedule? Group of answer choices SWOT analysis Monte
Which risk analysis tool is most commonly used to determine the probability of a project completing on schedule?
Group of answer choices
SWOT analysis
Monte Carlo simulation
Risk matrix
Risk register