Question: Which risk handling mode is a project manager using if he / she throws out one of three designs for a new product? a .

Which risk handling mode is a project manager using if he / she throws out one of three designs for a new product? a. Acceptance / Assumption b. Avoidance c. Control / mitigation d. Transfer