Question: Which risk-response option would best describe when a project manger decide that the the cost to mitigate risk is higher than cost to bear the
Which risk-response option would best describe when a project manger decide that the the cost to mitigate risk is higher than cost to bear the risk, then the best response is to take and continually monitor the risk O Rsk mitigation Risk transfer O Risk acceptance O Risk monitoring O Rsk avoidance