Question: Which scheduling technique should be employed when due dates are important for a job order? a . forward scheduling b . dispatching c . backward

Which scheduling technique should be employed when due dates are important for a job order?
a. forward scheduling
b. dispatching
c. backward scheduling
d. loading
e. master scheduling