Question: Which statement about allocation of risk regarding differing site conditions and bidding is not correct? A contractor bids higher for a project on which he
Which statement about allocation of risk regarding differing site conditions and bidding is not correct?
A contractor bids higher for a project on which he assumes more risk regarding differing site conditions.
Unit prices in a bid help to mitigate the risk of differing site conditions to an owner and a contractor.
A contractors bid will be affected by the allocation of risk.
Differing site conditions are typically less of a source of contention for cost-plus contracts than for lump-sum contracts.
An owner should expect higher bids if he accepts more of the risk for himself regarding differing site conditions