Question: Which statement about allocation of risk regarding differing site conditions and bidding is not correct? A contractor bids higher for a project on which he

Which statement about allocation of risk regarding differing site conditions and bidding is not correct?

A contractor bids higher for a project on which he assumes more risk regarding differing site conditions.

Unit prices in a bid help to mitigate the risk of differing site conditions to an owner and a contractor.

A contractors bid will be affected by the allocation of risk.

Differing site conditions are typically less of a source of contention for cost-plus contracts than for lump-sum contracts.

An owner should expect higher bids if he accepts more of the risk for himself regarding differing site conditions

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!