Question: Which statement below is NOT correct? A . The stakeholder engagement assessment matrix is used as a data representation tool to record and monitor their
Which statement below is NOT correct?
A
The stakeholder engagement assessment matrix is used as a data representation tool to record and monitor their support levels.
B
For each activity, the RACI chart should include only one stakeholder who assumes the role for accountability.
C
The responsibility assignment matrix illustrates each team member's and relevant stakeholders' roles and responsibilities in each project activity.
D
The stakeholder engagement matrix is used to keep the track of power and interest levels of all the stakeholders.