Question: Which statement best describe a time constrained project A. resources cannot be added B Resources can be added c have the ability to improve utilization

  1. Which statement best describe a time constrained project

A. resources cannot be added

B Resources can be added

c have the ability to improve utilization of resources

d. Imposed end date