Question: Which statement best describes how fast - tracking works on resource - constrained projects? Multiple choice question. Finish - to - start relationships are changed

Which statement best describes how fast-tracking works on resource-constrained projects?
Multiple choice question.
Finish-to-start relationships are changed to start-to-start.
The cost is increased in order to reduce project completion time.
Critical activities are done sequentially.