Question: Which statement best describes the relationship between project crashing and the critical path? Group of answer choices Crashing is most effective for activities outside the

Which statement best describes the relationship between project crashing and the critical path?
Group of answer choices
Crashing is most effective for activities outside the critical path.
The critical path should be avoided when crashing a project.
Crashing is aimed at reducing the duration of activities on the critical path.
The critical path cannot be altered through crashing.