Question: Which statement is correct. The critical chain method: Group of answer choices helps planners to estimate the duration of activities more accurately. stresses that, in

Which statement is correct. The critical chain method:
Group of answer choices
helps planners to estimate the duration of activities more accurately.
stresses that, in order to finish the project on the project deadline (due date), all critical activities must be finished by their individual deadlines (due dates).
forces a person working on an activity to make a commitment on when he/she will finish the work.
ensures that sufficient contingency reserve is built into the schedule of each individual activity.
implies that activities are done as early as possible but with appropriately-sized buffers.
None of the above is correct.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!