Question: Which statement is correct. The critical chain method: Group of answer choices helps planners to estimate the duration of activities more accurately. stresses that, in
Which statement is correct. The critical chain method:
Group of answer choices
helps planners to estimate the duration of activities more accurately.
stresses that, in order to finish the project on the project deadline due date all critical activities must be finished by their individual deadlines due dates
forces a person working on an activity to make a commitment on when heshe will finish the work.
ensures that sufficient contingency reserve is built into the schedule of each individual activity.
implies that activities are done as early as possible but with appropriatelysized buffers.
None of the above is correct.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
