Question: Which statement is not true? Select one: A project needs to be formally approved by the sponsor and agreed upon by its stakeholders . The

Which statement is not true? Select one: A project needs to be formally approved by the sponsor and agreed upon by its stakeholders . The execution phase relies heavily on the planning phase. Monitoring and Controlling phases are sometimes combined with the Execution phase because they often occur at the same time A task " dependencymeans that a work task has two resources on it All are true statements