Question: Which statement is true about a change control board?A) A change control board identifies the changes that might potentially be required.B) A change control board

Which statement is true about a change control board?A) A change control board identifies the changes that might potentially be required.B) A change control board is led by the project manager.C) A change control board generates reports of the changes incurred on a project.D) A change control board is responsible for approving or rejecting change requests.