Question: Which statement is true regarding activities not on the critical path?A.They have less slack than activities on the critical pathB.They can be delayed limited amounts
Which statement is true regarding activities not on the critical path?A.They have less slack than activities on the critical pathB.They can be delayed limited amounts of time without causing a delay to the projectC.They usually cannot be delayedD.They are not important to the project