Question: Which statement regarding critical path and non - critical path is CORRECT? There may be more than one correct answer. Select ALL that apply. Which
Which statement regarding critical path and noncritical path is CORRECT?
There may be more than one correct answer. Select ALL that apply.
Which statement regarding critical path and noncritical path is CORRECT?
There may be more than one correct answer. Select ALL that apply.
Critical path is the path with the highest number of activities.
Only noncritical path activity can have positive slack time.
Critical path determines the completion time of the project.
Any delay occurs on a critical path activity will delay the entire project.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
