Which statement regarding critical path and non-critical path is CORRECT?
There may be more than one correct answer. Select ALL that apply.
Which statement regarding critical path and non-critical path is CORRECT?
There may be more than one correct answer. Select ALL that apply.
Critical path is the path with the highest number of activities.
Only non-critical path activity can have positive slack time.
Critical path determines the completion time of the project.
Any delay occurs on a critical path activity will delay the entire project.