Question: Which tab in the Project Options dialog box provides the option to calculate multiple critical paths? Group of answer choices Advanced Display Schedule Proofing
Which tab in the Project Options dialog box provides the option to calculate multiple critical paths?
Group of answer choices
Advanced
Display
Schedule
Proofing