Question: Which task is the bottleneck? Prepare Front Stitch Front & Back Iron Pack 5 Mins./Unit Prepare Back 4 Mins./Unit 12 Mins./Unit 5 Mins./Unit 10 Mins./Unit

Which task is the bottleneck? Prepare FrontWhich task is the bottleneck?

Prepare Front Stitch Front & Back Iron Pack 5 Mins./Unit Prepare Back 4 Mins./Unit 12 Mins./Unit 5 Mins./Unit 10 Mins./Unit