Question: Which task or tasks are not on the critical path? Update the project based on the following information and answer the following questions. Task 1
- Which task or tasks are not on the critical path?
Update the project based on the following information and answer the following questions.
-
- Task 1 is 100% complete
- Task 2 is a 100% complete, but the actual duration has been changed to 4 days
- Summary Task 1 is 100% complete
- What is the project finish date?
- By performing the above update on your project, what is the difference (how many days) between the current finish date and the finish date on your original baseline?
- Based on your updates, what is the total progress (percentage) on Summary Task 2?
- Based on your updates, what is the total progress (percentage) on the whole project?
Step by Step Solution
There are 3 Steps involved in it