Question: Which task or tasks are not on the critical path? Update the project based on the following information and answer the following questions. Task 1

  1. Which task or tasks are not on the critical path?Which task or tasks are not on the critical path?

Update the project based on the following information and answer the following questions.

    1. Task 1 is 100% complete
    2. Task 2 is a 100% complete, but the actual duration has been changed to 4 days
    3. Summary Task 1 is 100% complete
  1. What is the project finish date?
  2. By performing the above update on your project, what is the difference (how many days) between the current finish date and the finish date on your original baseline?
  3. Based on your updates, what is the total progress (percentage) on Summary Task 2?
  4. Based on your updates, what is the total progress (percentage) on the whole project?
Predecessors LITTLE Duration 18 days 5 days 2 days 3 days O days Start Wed 3/27/19 Wed 3/27/19 Wed 3/27/19 Fri 3/29/19 Tue 4/2/19 Finish Fri 4/19/19 Tue 4/2/19 Thu 3/28/19 Tue 4/2/19 Tue 4/2/19 3 st 5 Task Mode - Task Name Project Simple Summary #1 Task 1 Task 2 Summary #1 Complete Summary #2 Task 3 Task 4 Task 5 Summary #2 Complete Summary #3 Task 6 Task 7 Task 8 Finish 6 days 3 days 4 days 2 days 0 days Wed 4/3/19 Wed 4/3/19 Wed 4/3/19 Tue 4/9/19 Wed 4/10/19 Wed 4/10/19 Fri 4/5/19 Mon 4/8/19 Wed 4/10/19 Wed 4/10/19 st 8 9 10 7 days 3 days 2 days 2 days o days BEITE Thu 4/11/19 Thu 4/11/19 Tue 4/16/19 Thu 4/18/19 Fri 4/19/19 Fri 4/19/19 Mon 4/15/19 Wed 4/17/19 Fri 4/19/19 Fri 4/19/19 12 13 14

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!