Question: Which technique involves doing activities in parallel that one would normally do in sequence? Select one: A . Critical Chain Scheduling B . Critical Path
Which technique involves doing activities in parallel that one would normally do in sequence?
Select one:
A Critical Chain Scheduling
B Critical Path Analysis
C Crashing
D Fast Tracking