Question: Which two activities take place during Team Breakout #1 on the first day of Program Increment (PI) Planning? (Choose two.) Draft objectives and uncommitted objectives
Which two activities take place during Team Breakout #1 on the first day of Program Increment (PI) Planning? (Choose two.)
- Draft objectives and uncommitted objectives are written
- Teams use color-coding for their backlog items as a reminder that they are required to have all backlog item types on their planning boards
- Draft objectives are written but do not include exploration Enablers
- All teams' planning boards are visible and use the same color coding
- Risks on the teams' planning boards are resolved by the Release Train Engineer