Question: Which two Process Groups are engaged in the Executing phase? Directing and Managing Project Work and Monitoring and Controlling Project Work Initiating and Closing Managing

Which two Process Groups are engaged in the Executing phase?

  • Directing and Managing Project Work and Monitoring and Controlling Project Work
  • Initiating and Closing
  • Managing Scope and Quality
  • Executing and Monitoring and Controlling

What are the three project documents that are developed in the Executing phase?

  • Quality Reports, Control Metrics, and Risk Report
  • Team Charter, Risk Register, and Project Calendar
  • Change Log, Issues Log, and Lessons Learned Register
  • Activity Report, Attributes, and Milestone List

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!