Question: Which work breakdown structure ( WBS ) component is a placeholder for future work that doesn't contain detailed scheduled activities? A . Work package B

Which work breakdown structure (WBS) component is a placeholder for future work that doesn't contain detailed scheduled activities?
A. Work package
B. Planning package
C. Line-item risk
D. Contingency reserve
2. Which of the following is an example of a variable project cost?
A. Equipment
B. Facilities
C. People
D. Reserves
3. The ________ is where the organizational breakdown structure (OBS) and the work breakdown structure (WBS) intersect and establishes ownership and budget for each work effort.
A. Work package
B. Cost baseline
C. Activity
D. Control account
4. You are including activities for conducting testing and inspections throughout the project. These are considered to be _________.
A. prevention costs
B. line item risk activities
C. costs of quality
D. indirect project costs
5. What is the time-phased budget excluding the management reserves?
A. Cash flow
B. Budget at completion (BAC)
C. Control account
D. cost baseline

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!