Which work breakdown structure WBS component is a placeholder for future work that doesn't contain detailed scheduled activities?
A Work package
B Planning package
C Lineitem risk
D Contingency reserve
Which of the following is an example of a variable project cost?
A Equipment
B Facilities
C People
D Reserves
The is where the organizational breakdown structure OBS and the work breakdown structure WBS intersect and establishes ownership and budget for each work effort.
A Work package
B Cost baseline
C Activity
D Control account
You are including activities for conducting testing and inspections throughout the project. These are considered to be
A prevention costs
B line item risk activities
C costs of quality
D indirect project costs
What is the timephased budget excluding the management reserves?
A Cash flow
B Budget at completion BAC
C Control account
D cost baseline
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock