Question: While constructing a roof for a large building, the project team has identified the risk of a snowstorm. Due to the region in the country
While constructing a roof for a large building, the project team has identified the risk of a snowstorm. Due to the region in the country and the time of the year, the team has decided to take no action or preparations for the snowstorm. What risk response strategy is the team using?
Acceptance
Mitigation
Avoid
Enhance