Question: While developing the procurement strategy, the project manager requests that you use a contract type that will obligate the seller to accept all liabilities of
While developing the procurement strategy, the project manager requests that you use a contract type that will obligate the seller to accept all liabilities of poor workmanship, errors, and consequential damages in the project. Which of the following contract type will you select?
a. Fixed Price
b. Time and Materials
c. Best price
d. Cost reimbursable