Question: While doing earned value calculations, the project manager records the following data: AC=4,000,000,CV=-500,000,SPI=1.12 and BAC=9,650,000. Calculat earned value (EV) A) $3,500,000 B) $5,650,000 C) $3,800,000
While doing earned value calculations, the project manager records the following data: AC=4,000,000,CV=-500,000,SPI=1.12 and BAC=9,650,000. Calculat earned value (EV) A) $3,500,000 B) $5,650,000 C) $3,800,000 D) $4,480,000 Question 6 (1 point) During which stage of team development is high performance not a top priority an attention is devoted to wrapping up the proiect