Question: While efficiency in the production operation is important to profitability, ACME Valve is also known for high quality finished products. Parts that do not meet

While efficiency in the production operation is important to profitability, ACME Valve is also known
for high quality finished products. Parts that do not meet specifications cannot be reworked, so
any out of spec parts eat into the companys profitability both for the raw material cost and the
machine time to produce them. Drills can become dull after producing so many parts, typically
resulting in oversized holes. Machines can get out of calibration as well. For the parts in your
department the critical dimension is the diameter of the center hole and design specifications
require that tolerances be maintained within .005. To ensure that quality is maintained, one part
from each machine is sent to the Quality Control Lab each hour and carefully measured and its hole
diameter recorded into the QC database for each machine.
To better learn how the QC process is coordinated with the production areas, you are spending a
day in the Quality Control Lab. In looking at the data for one of the machines making aluminum
flanges, you notice some variation and possibly some trending in the data. The data points for this
machine over the last 24 hours are shown in the control chart below
Page 5
Hole ID (in.)- Machine #2
2.51
2.505
2.5
2.495
2.49
2.485
123456789101112131415161718192021222324
The individual observations are plotted by time (i.e. observations 1-24). The upper and lower
control limits based on required tolerances for the center hole diameter are shown by the
horizontal lines. Looking at this graph, answer the following questions:
a) What if anything should be done at observation 6?
b) At what point (which sample #) should the QC Lab alert manufacturing that the process
may be out of control or nearly so?
c) Did this process actually become out of control and if so how many parts potentially may
need to be scrapped?
d) What could account for the sudden change between samples 23 & 24.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!