Question: While managing your project, you noticed that the project is running behind schedule. You decided to start the next phase before the current phase is
While managing your project, you noticed that the project is running behind schedule. You decided to start the next phase before the current phase is completed in order to bring the project back on track. This technique is called q,a) Fast trackingb) Overloadingc) Expeditingd) Schedule acceleratinge) Crashing