Question: While performing a quality audit on a procurement, a team member discovers an issue tha requires a change to code. This change will affect future

While performing a quality audit on a procurement, a team member discovers an issue tha requires a change to code. This change will affect future procurement work, as this code may be reused. The change control process is implemented, and the change is approved. Which performance domain is being performed in this situation? A) Uncertainty B) Project Work C) Planning D) Delivery