Question: While performing the 1 . 3 Pin small barges together to form raft work package, inclement weather conditions caused work to take 5 days

While performing the "1.3 Pin small barges together to form raft" work package, inclement weather conditions caused work to take 5 days instead of 1 as originally scheduled. Update the schedule based on this change.
Which of the following is true about the impact of this change on the project schedule?
Note: Before you proceed to the next question, close the file without saving changes, then reopen it to return to the original schedule. OR: change the task duration back to 1 day.
Group of answer choices
The end date of the project changed to 12/17/14
The end date of the project changed to 12/29/14
The end date of the "1.3 Pin small barges together to form raft" work package changed to 12/14/14
The end date of the project changed to 1/13/15

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!