Question: While performing the work, all the activities in the baseline plan must be performed in accordance toQuestion 5 options:what the person responsible for the activity

While performing the work, all the activities in the baseline plan must be performed in accordance toQuestion 5 options:what the person responsible for the activity wants.lesson learned from prior projects.how the sponsor has completed all their projects in the past.the project schedule and technical specifications.