Question: While preparing for a product launch, the project manager conducts a review and identifies a potential blocker to the launch. What should the project manager

While preparing for a product launch, the project

While preparing for a product launch, the project manager conducts a review and identifies a potential blocker to the launch. What should the project manager do? Update the risk register Identify project risks. Perform a nisk analysis. Conduct a risk workshop