Question: While preparing technical documentation in an engineering project, you realized that the construction effort was underestimated. After further analysis, you concluded that the approved schedule

While preparing technical documentation in an engineering project, you realized that the construction effort was underestimated. After further analysis, you concluded that the approved schedule cannot be met without redefining the project. As a project manager, how should you proceed?
Eliminate scope components that were required by your organization but were not required by the customer
Review the project schedule, document issue in a status report, and gather lessons learned regarding the schedule variance
Discuss the issue and alternative solutions with the sponsor.
Request additional funding from the sponsor to compress the schedule
 While preparing technical documentation in an engineering project, you realized that

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!