Question: While smoothing the production load, lot splitting _____. A. involves an additional setup but results in shorter throughput times because only part of the lot
While smoothing the production load, lot splitting _____.
| A. | involves an additional setup but results in shorter throughput times because only part of the lot is processed on each machine. | |
| B. | involves breaking up the order and running part of it at an earlier (or later) time in the schedule. | |
| C. | splits the operation to more than one lot. | |
| D. | reduces the lead time, sends pieces to the second operation before the entire lot is completed on the first operation. | |
| E. | sends the lot to two different machines for the same operation. |