Question: While we do not have any specific timing as to when the Operation planning should commence, the ideal time to consider this aspect would be:

While we do not have any specific timing as to when the Operation planning should commence, the ideal time to consider this aspect would be:

A. It is something that operation teams have to manage and it is best left to the operation team.

B. to plan along with the project planning

C.plan after the project has been completed

D. this planning has no relevance to the project work hence no planning is required

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!