Question: While working on a new server upgrade project, the project manager calculates the SPI of the project to be 1 . 3 . The project
While working on a new server upgrade project, the project manager calculates the SPI of the project to be The project sponsor would like an explanation for why the SPI is that high. What would be the project managers best response?