Question: White reviewing prototypes, the quality team found some deviations that do not affect the main functionality but have the potential to be an issue in
White reviewing prototypes, the quality team found some deviations that do not affect the main functionality but have the potential to be an issue in the future. To avod major probiems in the future, the team recommends corrective actions that will require additional funds The project is already struggung to stay on budget and has even used some of the contingency rosarves What should the project manager do? Ask the product designer why the deviation was not considered in the design phase Ask the quality team to discard the sample and test again with a new sample Evaluate and intiate the change request process with the stakeholders Report to the project sponsor that the product is working and the project is struggling with the budget