Question: Why are CPM and PERT not used to solve resource constrained project scheduling problems? In PERT and CPM , precedence relationships are not modelled. In

Why are CPM and PERT not used to solve resource constrained project scheduling problems?
In PERT and CPM, precedence relationships are not modelled.
In PERT and CPM, time of activities do not depend on the amount of resources used.
The time taken by activities do not depend on the availability of resources
PERT and CPM assume unlimited availability of resources