Question: Why are estimates done during project resource management planning better than those done during annual operating planning? Group of answer choices 1.The project team members

Why are estimates done during project resource management planning better than those done during annual operating planning? Group of answer choices

1.The project team members are generally using more sophisticated estimation tools and techniques.

2.The human resource management systems used by project managers are superior.

3.Functional managers have better visibility into resource availability and are more focused.

4.The project team members are making use of decision analysis modeling tools.