Question: Why do alternative project delivery methods such as Design Build or CM have the ability to positively influence a project's cost? Group of answer choices
Why do alternative project delivery methods such as Design Build or CM have the ability to positively influence a project's cost? Group of answer choices The contractor is provided more design information in these delivery methods. The contractor is brought into the project earlier in the design phase and can provide input on design decisions that can influence cost. In these delivery methods the contractor controls the design. These delivery methods fix the cost of the project so there are no change orders