Question: Why do project leaders use resource calendars when developing their schedules? a to see when resources will be available to work on project activities b
Why do project leaders use resource calendars when developing their schedules? a to see when resources will be available to work on project activities b to see when a project will start and finish c to see how many resources they will need to finish project work d Project leaders would not use resource calendars when creating their schedules
Step by Step Solution
There are 3 Steps involved in it