Question: Why does a budget need to be closely integrated with the project schedule? Choose the best answer. the budget is a precedent for scheduling on

Why does a budget need to be closely integrated with the project schedule? Choose the best answer. the budget is a precedent for scheduling on the critical path. estimates for costs are not made until later. costs are allocated to the period in which they occur. budget constraints can require schedule changes such as completing a task slowly to minimize financing costs