Question: Why does the scheduling function depend on the planning function? Which one must be done first? Why? 2. Describe what an activity estimated duration is.
Why does the scheduling function depend on the planning function? Which one must be done first? Why?
2. Describe what an activity estimated duration is. How is it determined?
Refer to Figure 5.4. Why is the earliest start time for Review Comments & Finalize Questionnaire day 33? Why is the earliest finish time day 38
.
From your experience, describe how you have used a project control process. If you did not use continual monitoring of the progress, how would it have helped improve the project s success if you did use it?
Who can initiate changes to a project schedule? Describe why and when changes would occur in a project. How are the network diagram and schedule updated to reflect the changes