Question: Why is it critical to develop a time - phased baseline? multiple choice It increases free slack ( but not total slack ) . It
Why is it critical to develop a timephased baseline?
multiple choice
It increases free slack but not total slack
It decreases the risk by increasing flexibility.
It levels resources automatically.
It measures how much work is accomplished for the money spent.