Question: Why should project task time, cost, and resource estimates be based on normal conditions? Multiple select question. Normal conditions minimize time and cost totals. Normal

Why should project task time, cost, and resource estimates be based on "normal conditions"?
Multiple select question.
Normal conditions minimize time and cost totals.
Normal conditions overestimate profit.
Normal conditions provide a common frame of reference for interpreting the estimates.
Normal conditions prevent overly optimistic estimates.