Question: Why would a summary task have a duration that includes a question mark? a The summary task duration value needs to be entered. b A
Why would a summary task have a duration that includes a question mark?
a
The summary task duration value needs to be entered.
b
A subtask below the summary task has an estimated value.
c
The summary task and subtasks are not completed.
d
The summary task is missing a milestone subtask.