Question: Widget Co . needs to design a product layout for a new product, the amazing Thatsit. The company plans to use this new production line
Widget Co needs to design a product layout for a new product, the amazing "Thatsit". The company plans to use this new production line eight hours a day in order to meet projected demand of units per day. The following table describes the tasks involved in the production of a "Thatsit".
TASK PREDECESSOR TIMEseconds
U
V U
W V
X V
Y W
Z X Y
For output to equal projected demand, what will be the last task performed at the second workstation of the production line which uses the minimum number of workstations? Hint: Use the heuristic rule "Assign the task with the most followers."
Balancing Formula
Multiple Choice
Y
U
X
V
W
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock