Question: Widgets are made in 3 steps. Step 1 has 4 workers and needs 6 minutes per unit. Step 2 has 4 workers and uses 5
Widgets are made in 3 steps. Step 1 has 4 workers and needs 6 minutes per unit. Step 2 has 4 workers and uses 5 minutes per unit. Step 3 has 3 workers and needs 4 minutes per unit.
Assuming unlimited demand, what is the flowrate ?
What is the utilization of step 1? %
Due to the snow, demand was only 11 units. What is the flowrate?