Question: Will Project Creep Cost You or Create Value), the author suggests that a decision to approve a project add-on should be based upon The cost
Will Project Creep Cost You or Create Value), the author suggests that a decision to approve a project add-on should be based upon The cost of the add-on work The length of time the add-on work is estimated to take The wishes of the sponsor None of these items is an appropriaite basis for approval of add-on work Careful ROI analysis of the add-on work