Question: will rate Develop a material tequirements plan for component H. Lead times for the end item and each component except B are one week. The



Develop a material tequirements plan for component H. Lead times for the end item and each component except B are one week. The lead time for B is three woeks. Sixty units of A are needed at the start of week 8 . There are currently 15 units of B on hand and 130 of E on hand, and 50 units of H are in production and will be completed by the start of week 2 (Leave no cells blank - be certain to enter "o" wherever required.) Master Schedule \begin{tabular}{|c|c|c|c|c|c|c|c|c|c|} \hline ALT =1 & \begin{tabular}{l} Bugnning \\ mimention \end{tabular} & 1 & 2. & 3 & 4 & 5 & 6. & 7 & a \\ \hline \multicolumn{10}{|l|}{ Gross tequirements } \\ \hline \multirow{2}{*}{\multicolumn{10}{|c|}{\begin{tabular}{l} Schectiled receipts \\ Propeded on hand \end{tabular}}} \\ \hline \multicolumn{8}{|l|}{ Propeded on hand } & & \\ \hline \multicolumn{10}{|l|}{ Net tequirenents } \\ \hline \multicolumn{10}{|l|}{ Planned onder receipts:- } \\ \hline Planned order rekases & & & & & & & & & \\ \hline \end{tabular} \begin{tabular}{|c|c|c|c|c|c|c|c|c|c|} \hline & & 1 & 2 & 3 & 4 & 5 & i. & 1 & b \\ \hline \multicolumn{10}{|l|}{ Gross requirements } \\ \hline \multicolumn{10}{|l|}{ Sidiestuled receepts } \\ \hline \multicolumn{10}{|l|}{ Projected on hand } \\ \hline \multicolumn{10}{|l|}{ Netrequirements } \\ \hline \multicolumn{10}{|l|}{ Planned-order receipts } \\ \hline Planned-order teleases & & & & & & & & & \\ \hline \end{tabular}
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts