Question: Willow Inc. has provided the following information: Standards: Per unit Direct materials 10 lb @ $3.50/lb $ 35.00 Direct labor 2 hours @ $23.50/hour 47.00
Willow Inc. has provided the following information:
| Standards: | Per unit | ||
| Direct materials | 10 lb @ $3.50/lb | $ | 35.00 |
| Direct labor | 2 hours @ $23.50/hour | 47.00 | |
| Variable overhead | 2 hours @ $17/hour | 34.00 | |
| Fixed overhead | 25.00 | ||
| Total | $ | 141.00 | |
Budgeted production = 7,300 units
| Actual results | ||||
| Materials | 75,220 | lbs | $ | 261,490 |
| Direct labor | 14,400 | actual hours | $ | 328,445 |
| Variable overhead | $ | 251,330 | ||
| Fixed overhead | $ | 179,440 | ||
| Units produced | 7,600 | units | ||
a. Calculate the direct materials price variance. (Do not round your intermediate calculations. Indicate the effect of variance by selecting "Favorable", "Unfavorable", or "None" for no effect (i.e., zero variance).) b. Calculate the direct materials quantity variance. (Indicate the effect of variance by selecting "Favorable", "Unfavorable", or "None" for no effect (i.e., zero variance).) c. Calculate the direct labor rate variance. (Do not round your intermediate calculations. Indicate the effect of variance by selecting "Favorable", "Unfavorable", or "None" for no effect (i.e., zero variance).) d. Calculate the direct labor efficiency variance. (Indicate the effect of variance by selecting "Favorable", "Unfavorable", or "None" for no effect (i.e., zero variance).) e. Calculate the variable overhead rate variance. (Do not round your intermediate calculations. Indicate the effect of variance by selecting "Favorable", "Unfavorable", or "None" for no effect (i.e., zero variance).) f. Calculate the variable overhead efficiency variance. (Indicate the effect of variance by selecting "Favorable", "Unfavorable", or "None" for no effect (i.e., zero variance).) g. Calculate the fixed overhead spending variance. (Indicate the effect of variance by selecting "Favorable", "Unfavorable", or "None" for no effect (i.e., zero variance).)