Question: Wills Welded Widgets (WWW) makes its Q Model from components R, S, and T. Component R is made from 3 units of component X and

Wills Welded Widgets (WWW) makes its Q Model from components R, S, and T. Component R is made from 3 units of component X and 3 unit of component Y. Component T is made from 1 unit of component V and 2 units of component Z.

Using the given information and the beginning inventories 70 units of component T and 190 units of component R, calculate the minimum replenishment time for the 70 Q Models.

Item

Usage per Parent

Lead Time (weeks)

Q

1 3

R

3 6

S

3 5

T

1 4

X

3 4

Y

3 5

V

1 5

Z

2 6

The cumulative lead time is enter the cumulative lead time in weeks weeks.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!